330 kV Interconnection Line Ikeja West (Nigeria) - Sakete (Benin) |
| |
255 kV Bobo Dioulasso - Ouagadougou Transmission Line (Burkina Faso)
|
| |
330 kV Volta - Mome Hagou-Sakete (Ghana-Togo-Benin Interconnection) |
| |
330 kV WAPP NorthCore Line : Birnin Kebbi - Bemberke - Niamey - Ouagadougou |
| |
OMVS-SOGEM Felou 60 MW Hydro Project |
| |
OMVG Project |
| |
225 kV Bolgatanga - Ouagadougou Line (Ghana-B. Faso Interconnection) |
| |
Han - Bobo Diolasso - Sikasso - Bamako Line (Ghana - Burkina Faso - Mali) |
|
330 kV LINE IKEJA WEST(Nigeria) - SAKETE(Benin) |
| |
|
| Project Cost : 40 US$ millions
|
Status:
Line was officially commissioned on February 13th, 2007.
The project was being implemented in 4 lots:
- Lot A1 : 330 kV Line within Nigeria
- Lot A2 : 330 kV Line within Bénin
- Lot B1 : Ikeja West Substation, Nigeria
- Lot B2 : Sakété Substation, Bénin
Activity:
- Lot A1: being implemented by SAE;
- Lot A2: being implemented by INEO;
- Lot B1: being implemented by AREVA;
- Lot B2: being implemented by CEPEL;
Supervising Engineer = Lahmeyer International |
|
| |
| |
 |
| Project Cost : 90 US$ millions
Funding Sources : AfD, WB, Danish Credit, Nordic Fund, FMO, DANIDA |
Status / Activity:
Recruitment of Contractors in progress.
Upstream works on 90 - 33 kV medium voltage network around Ouagadougou and rural electrification of 5 localities along the route of the line being financed by Nordic Fund, together with a consortium of Danish financiers and SONABEL are in progress.
Commissioning of the project is now expected in the fourth quarter of 2008.
Next Steps:
Finalization of Contractor selection process and commence works
330kv Volta-Mome Hagou Sakete(Ghana-Togo Benin Interconnection) |
| |
 |
| |
| Project Cost : 97 US$ millions
Funding Sources : WB, AfDB, IsDB, BOAD, EBID |
Status :
- WB loan for financing of VRA and CEB approved under APL-1 (tranche 2).
- AfDB loan for financing approved.
- BOAD loan for financing approved.
- IsDB and EBID loans being finalized
Detailed Design and Environmental studies are completed.
Commissioning of the project is expected in the fourth quarter of 2009.
Activity:
Finalization of ISDB and EBID loans financing process of project. |
|
| |
|
|
|
| |
|
|
|
|